Edited by the Printingtalk editorial team Nov 15, 2004

Achieving a further milestone in the construction of its Sheffield plant, the Polestar Group has this week taken possession of the first two press bases.

Achieving a further milestone in the construction of its Sheffield plant, the Polestar Group has taken possession of the first two press bases.

Installation of the two 3.88 metre-wide Cerutti presses will begin in next month.

A third press is scheduled for installation in May 2005.

Project managing director Mike Young said: "We continue to meet our targets and deadlines on this project and are on course for completion next month.

The next major phase will be the installation of equipment, which is when we will really begin to see the capability and scale of this factory." Polestar took possession of the pre-press area from the contractors at Sheffield last month.

Not what you're looking for? Search the site.

Back to top Back to top

Contact Polestar

Related Stories

Contact Polestar
Newsletter sign up

Request your free weekly copy of the Printingtalk email newsletter ...

A Pro-talk Publication

A Pro-talk publication